• CapEx: $10 billion
  • Jobs: 1,067 new (200 direct, 867 indirect)
  • Product: Liquified natural gas with CCS technology
  • Location: Cameron Parish / Southwest Region
  • Project overview:
    • New liquefied natural gas facility in Cameron Parish that will employ carbon capture and sequestration technology (CCS) to reduce carbon dioxide (CO2) emissions.
    • Named CP2, will have a nameplate capacity of 20 million metric tonnes per annum (MTPA) of LNG. 
    • The CCS process will be used to capture and store underground an estimated 500,000 tons of CO2 emissions from the facility annually. 
    • The complex will be located on 650 acres in Cameron, including 170 acres on Monkey Island, providing CP2 with direct access to the deep-water Calcasieu Ship Channel.
  • Estimated Completion:  unknown

Company website: www.venturegloballng.com